As the Beresteyn redevelopment takes shape, you can find out all the latest planning and construction news right here. Check back in to stay up to date, and visit the timeline to see the latest project schedule.

01 May 2024

UPDATE PARKING GARAGE

In our message from April 2nd, we reported that the remediation work on the ground floor of the parking garage would take place in week 18. This has been moved to week 20. An aggregate will be required for this, which may cause noise disturbance. The aggregate will be placed on the station side, probably […]

02 Apr 2024

UPDATE CONSTRUCTION WORK PARKING GARAGE

Completion of Work In week 18, remediation work will take place on the ground floor of the parking garage. This will require the use of a generator, which may cause noise disturbance. By week 20 (mid-May) at the latest, we will complete the work in the basement, and it will be reopened. By the end […]

11 Dec 2023

STATUS OF BERESTEYN DEVELOPMENT

The development of Beresteyn depends on the configuration of the Stationsplein (Station Square). City Council Decision on Stationsplein On Tuesday, November 21, the city council made a decision regarding the Stationsplein. From three options, the council chose the ‘good neighbors’ variant. To enhance access to the station for cyclists, two options will be further developed. […]

19 Oct 2023

PARKING GARAGE CLOSURE

The garage will be closed from Thursday, November 9th, at 8:00 PM until (at the latest) Friday, November 24th. – If you need your car during this period, you will need to park it elsewhere. The nearest parking garage is Cronjé Parking Garage, located at Kleverlaan 12. – If you don’t need your car during […]

18 Jul 2023

UPDATE CONSTRUCTION WORK PARKING GARAGE

On Monday, July 24th, the contractor will resume the construction work on the ground floor of the parking garage. Floor Removal A different method has been chosen for removing the floor. Instead of chiseling, a machine will be used to spray high-pressure water. This is expected to significantly reduce noise pollution for the residents of […]

06 Jun 2023

UPDATE 2

Starting from tomorrow, June 7th, until the end of next week at the latest, localized excavation work will be carried out. This may cause noise disturbances. The previously announced work did not take place.

24 May 2023

UPDATE 1

From Thursday 25 May, there will be noise nuisance again: demolition of the second part of the ground floor will then start. The demolition work will take approximately 5 working days. The work that will take place from that moment on is mainly aimed at repair and not at demolition. The level of noise nuisance caused […]

21 Mar 2023

ERROR MESSAGE

On March 9, 2023, Vastint Netherlands emailed a letter to the Owners Association (VvE), VvE Management, and the tenants of the Beresteyn complex regarding the construction activities in the parking garage. This letter indicated that questions and comments could be sent to bouw@beresteynhaarlem.nl. Due to technical issues, however, the email address only became operational on […]

20 Mar 2023

PARKING GARAGE STATIONSPLEIN

Since December 2020, Vastint has been the owner of the Beresteyn building complex located at Stationsplein in Haarlem. Vastint intends to redevelop this complex. In anticipation of this, Vastint will commence the renovation of the parking garage starting from March 20. What are we going to do? Extensive maintenance of the interior of the parking […]

13 Sep 2022

INTEGRATED AREA VISION

Haarlem’s station district is to undergo a transformation. The entire area will be radically reshaped, and for the Municipality of Haarlem this meant that an area vision had to be developed. This vision forms the compass for the step-by-step development of the district and brings together all aspects of the city.

13 Sep 2022

BERESTEYN HAARLEM

In December 2020, Vastint Netherlands became the owner of the Beresteyn building complex, located at the Stationsplein in Haarlem. Vastint Netherlands intends to redevelop the entire area, whereby the existing multifunctional complex of 36,400 m2 in total will undergo a complete transformation.