01 May 2024
UPDATE PARKING GARAGE
In our message from April 2nd, we reported that the remediation work on the ground floor of the parking garage would take place in week 18. This has been moved to week 20. An aggregate will be required for this, which may cause noise disturbance. The aggregate will be placed on the station side, probably for a duration of 3 days.
The further planning remains unchanged:
- By the end of week 20 (mid-May), we will complete the work in the basement. The basement will then reopen.
- By the end of June 2024, all work will be completed. The parking garage will then reopen and be easily accessible.